SCPC spent around $39 million in operating expenditure and more than $3 million in capital expenditure in first half of 2023

Baku, August 3, AZERTAC

In the first half of 2023, the South Caucasus Pipeline Company (SCPC) spent around $39 million in operating expenditure and more than $3 million in capital expenditure in total, bp Azerbaijan told AZERTAC.

“During the first half of 2023, the daily average export throughput of the SCP was 60.7 million cubic metres of gas per day,” the company said.

“The SCP has been operational since late 2006, transporting Shah Deniz gas to Azerbaijan, Georgia and Türkiye. The expanded section of the pipeline commenced commercial deliveries to Türkiye in June 2018 and to Europe in December 2020,” the company added.